| |
| Constitution |
 |
| Operator: | Anadarko |
| Water Depth: | 1,554 m / 5,128 ft |
| Region: | N. America - US GOM |
| Country: | US |
| Last Updated: | Mar 12, 2012 (view update history) |
|
Located in the Gulf of Mexico in 5,000 feet (1,524 meters) of water at Green Canyon Blocks 679 and 680, the Constitution field has estimated proven and probable reserves of approximately 110 MMboe. Anadarko owns and operates the Constitution field with 100% interest.
The initial well, drilled to a depth of 13,727 feet (4,184 meters) by the semisubmersible Noble Amos Runner, encountered more than 100 feet (30 meters) of net oil pay in a shallow Plio-Pleistocene objective. The second well, located approximately 4,000 feet (1,219 meters) northwest of the initial exploratory well and drilled to a depth of 15,213 feet (4,637 meters), encountered approximately 375 feet (114 meters) of net oil pay in Plio-Pleistocene sands. Discovery of the Constitution field was confirmed by ...
Located in the Gulf of Mexico in 5,000 feet (1,524 meters) of water at Green Canyon Blocks 679 and 680, the Constitution field has estimated proven and probable reserves of approximately 110 MMboe. Anadarko owns and operates the Constitution field with 100% interest.
The initial well, drilled to a depth of 13,727 feet (4,184 meters) by the semisubmersible Noble Amos Runner, encountered more than 100 feet (30 meters) of net oil pay in a shallow Plio-Pleistocene objective. The second well, located approximately 4,000 feet (1,219 meters) northwest of the initial exploratory well and drilled to a depth of 15,213 feet (4,637 meters), encountered approximately 375 feet (114 meters) of net oil pay in Plio-Pleistocene sands. Discovery of the Constitution field was confirmed by the second successful well, located in a separate fault block.
The field was discovered in 2003 and came online on March 27, 2006, reaching peak production volumes of roughly 40,000 bopd and 75 MMcf/d from all six dry-tree wells.
Truss Spar
In early 2004, Anadarko approved the development of its Constitution field utilizing a truss spar facility. The total project costs were approximately $600 million.
The Constitution truss spar was originally modeled after the company's Gunnison spar located on Garden Banks Block 668; however, following the discovery of Ticonderoga field in April 2004 by Kerr-McGee, Constitution's capacity was expanded to accommodate the additional production. As a result, Constitution has the capacity to process 70,000 bopd and 200 MMcf/d (6 MMcm/d) -- an increase in oil capacity of approximately 75% from its initial design. The spar is located in nearly 5,000 feet (1,524 meters) of water approximately 190 miles (306 kilometers) south of New Orleans, La.
The hull of the truss spar is 98 feet (30 meters) in diameter and 550 feet long. It has a displacement of 59,250 tons and a steel weight approaching 15,000 tons (13,608 tonnes). Technip built the hull at its Pori, Finland, yard. Technip also engineered and delivered the associated moorings and production riser system.
Gulf Island Fabrication built the topside for the Constitution truss spar platform in Houma, La. Also, Mustang Engineering provided engineering, procurement services and project management assistance for the topsides production facility.
Satellite Fields
Caesar
Another field currently utilizing the truss spar is Anadarko's Caesar field. It is located in approximately 4,500 feet (1,372 meters) of water, roughly 160 miles (257 kilometers) south of Houma, La.
Anadarko operates Caesar with a 33.75% working interest, Shell holds a 22.45% interest and Chevron holds 20.25%; and Statoil holds the remaining 23.55% interests.
Anadarko drilled three wells on the field and connected them to the Constitution Truss Spar. A fourth development well is expected to be drilled and completed later this year, as part of the planned Phase I development.
The field commenced production on March 7, 2012.
Ticonderoga
The Ticonderoga field is located on Green Canyon Block 768 in a water depth of 5,250 feet (1,600 meters). Anadarko operates the field and holds a 50% working interest; Noble Energy holds the remaining 50% interest.
The satellite field consists of two subsea wells tied-back to the Constitution spar facility.
The field contains estimated recoverable reserves of 30 to 50 MMboe, and commenced production Feb. 21, 2006.
Pipeline
Cameron Highway Oil Pipeline Company, a venture jointly owned by GulfTerra Energy Partners and Valero Energy Corporation, executed an agreement in 2004 with Kerr-McGee for the dedication and movement of crude oil production from the Constitution and Ticonderoga fields. GulfTerra installed, owns and operates the 70-mile (113-kilometer), 16-inch-diameter oil-gathering pipeline with a minimum capacity of 80,000 barrels that connects the fields with the Cameron Highway Oil Pipeline at the Ship Shoal Block 332B platform.
The Cameron Highway Oil Pipeline System is a 390-mile (628-kilometer) crude oil pipeline system with a capacity of approximately 500,000 barrels a day. The 30-inch-diameter pipeline segment of the system begins at Cameron Highway's Ship Shoal Block 332B platform 75 miles (121 kilometers) south of the Louisiana coastline and runs west 113 miles (182 kilometers) along the Outer Continental Shelf to GulfTerra's Garden Banks 72 hub platform. From Garden Banks Block 72, the pipeline goes northwest to the High Island Block A-5 platform, from which two 24-inch pipeline segments deliver oil to multiple delivery points in Texas City and Port Arthur, TX.
|
|
|
Anadarko Turns on Caesar/Tonga Taps in Deepwater GOM
Type: Production Start
Mar. 2012 - Anadarko commenced production at the Caesar/Tonga joint development in the Green Canyon area of the deepwater GOM on March 7, 2012. Production from Caesar/Tonga, with an estimated resource base of 200 to 400 million barrels of oil equivalent (boe), is expected to ramp up to approximately 45,000 boepd from the first three subsea wells. A fourth development well is expected to be drilled and completed later this year, as part of the planned phase I development. The subsea satellite wells are tied-back to the Constitution Spar floating production facility.
|
|
|
|
Anadarko Delays First Oil from Caesar/Tonga Project
Type: Status Update
Jan. 2011 - Anadarko announced that a mechanical issue involving the production riser system at the Caesar/Tonga project in the Gulf of Mexico will delay first production, which was expected in mid-2011. Recently, the production riser system underwent an extensive qualification program prior to installation, but Anadarko's recent hydro testing of the riser provided results that preclude it from being put into service. Anadarko plans to continue the completion activities as they work with the co-owners to secure a reliable alternative for the production riser. Caesar Tonga is a joint development project that began in early 2007 as a subsea tie-back to the Constitution Spar facility.
|
|
|
|
Anadarko to Further Develop Caesar Tonga Project
Type: Status Update
Mar. 2010 - Anadarko submitted a DOCD to MMS to further develop the Caesar-Tonga project. Under the DOCD, Anadarko will place four wells on production and install right-of-way and lease term pipelines. The work performed will take place on Green Canyon Blocks 683, 726 and 770. Caesar Tonga is a joint development project that began in early 2007 as a subsea tie-back to the Constitution Spar facility. First oil from the project is targeted for early 2011.
|
|
|
|
Anadarko Assessing Facilities after Gulf Storm
Type: Status Update
Nov. 2009 - Anadarko reported that it is assessing its facilities and anticipate returning personnel to operated platforms later today and tomorrow. The company will begin ramping up production as soon as it is safe to do so. Independence Hub, Constitution, Marco Polo and Neptune in the Gulf of Mexico were all shut in and evacuated late Sunday as a safety precaution due to Ida, which is now a tropical depression.
|
|
|
|
Aspen Aerogels Contracted for Insulation Work at Caesar-Tonga
Type: Contract Award
Nov. 2009 - Technip awarded Aspen Aerogels a contract to provide its Spaceloft aerogel thermal insulation for the Caesar-Tonga subsea tie-back to the Constitution Spar in the Gulf of Mexico. Caesar-Tonga is located in the Green Canyon area and the field development consists of two pipe-in-pipe insulated oil flowlines connected to two insulated flexible risers that originate from the spar. First oil is targeted for early 2011 via the Constitution Spar facility at Green Canyon Block 680.
|
|
|
|
Subsea 7 Tapped for Services at Caesar/Tonga Complex
Type: Contract Award
Nov. 2009 - Anadarko awarded an engineering, construction and installation contract to Subsea 7 for development of the Caesar/Tonga complex located in approximately 4,500 feet (1,372 meters) of water, roughly 160 miles (257 kilometers) south of Houma, La. Scheduled for start up in 2H 2010, the Subsea 7 workscope is to design, fabricate and install (using its pipelay and construction vessels) two manifolds and two riser base pipeline end manifolds, transport and install two flexible risers and to fabricate and install 10 jumpers, two main umbilicals and associated flying leads.
|
|
|
|
Caesar/Tonga Remains on Schedule
Type: Status Update
Nov. 2009 - Anadarko reports that its Caesar/Tong development project is on schedule. The GC683 No. 1 well is currently being drilled as an updip sidetrack to the original Caesar discovery well. Subsea construction is underway with first oil targeted for early 2011.
|
|
|
|
Noble Amos Runner to Drill Development Well at Caesar
Type: Development Activity
Oct. 2009 - The Noble Amos Runner semisub rig is slated to drill a development well at the Caesar development field, located on Green Canyon Block 683. Caesar is currently being developed as a subsea tie-back to the Constitution Spar, located on Green Canyon Block 680.
|
|
|
|
Caesar/Tonga Development Update
Type: Status Update
Aug. 2009 - Anadarko reports that construction activities began on the Constitution spar to prepare for the tie-back of the Caesar/Tonga field. Production handling agreements were approved by Anadarko and its partners. Preparations are under way to drill two wells (GC726 #1 and GC683 #1 sidetrack) and run casing to prepare them for production. Anadarko expects to begin this program during the 3rd quarter of 2009.
|
|
|
|
Noble Amos Runner to Drill Appraisal at Tonga West
Type: Appraisal Operations
Jul. 2009 - The Noble Amos Runner is slated to drill an appraisal well at Green Canyon block 726 on the Tonga West field. Tonga West is currently under development and is expected to start production as early as 2010.
|
|
|
|
Technip Bags 2 Subsea Contracts for Caesar/Tonga Development
Type: Contract Award
Jul. 2009 - Technip was awarded two lump sum contracts by Anadarko Petroleum Corporation as Unit Operator for the Caesar/Tonga oil field development in the Gulf of Mexico. This field spans Green Canyon Blocks 683, 726, 727 and 770, in water depths of around 1,500 meters (5,100 feet), and it will be tied-back to the Constitution Spar platform. The first contract covers the design and supply of the components for four pipe-in-pipe flowlines and the installation of these flowlines, representing a total of 27 miles (43 kilometers). The second contract covers the project management, engineering and fabrication of two control umbilicals and their termination hardware.
|
|
|
|
StatoilHydro Gives Go-Ahead for Caesar Tonga Dev't in GOM
Type: Development Activity
Apr. 2009 - The Anadarko-operated Caesar Tonga development consists of three discoveries, Tonga, Tonga West and Caesar. The three fields were combined into one project to be developed as a subsea tie-back to the Anadarko-operated Constitution Spar. The initial phase of development will consist of four wells with a combined average production of 40,000 bopd with first oil expected in 2011. StatoilHydro, Shell and Chevron also partner on the project.
|
|
|
|
Anadarko Expects Production at Constitution to be Restored in 1Q 2009
Type: Status Update
Feb. 2009 - Anadarko has reported in its 4Q Operations Report that the Constitution Spar is expected to be restored to full production by the end of 1Q 2009. The Constitution Spar was shut in for repairs after sustaining damage from Hurricane Ike. Third-party downstream infrustructures were also damanged and repairs on it is expected to be completed by the end of the quarter as well.
|
|
|
|
Anadarko Updates on its Caesar/Tonga Complex
Type: Status Update
Feb. 2009 - Anadarko announced success on Green Canyon 770 #1 appraisal well. The well was temporarily abandoned and will be used as a future producer. Anadarko continued with development activities at its Caesar/Tonga Complex in the 4th quarter 2008. Construction is underway at the Constitution spar to reduce future downtime when the subsea tieback is installed.
|
|
|
|
Constitution SPAR Facility Undergoing Repairs
Type: Status Update
Sep. 2008 - Anadarko reports that the Constitution SPAR facility in the western Gulf of Mexico on Green Canyon block 680 is currently undgoing repairs due to minor surface damage. Production is expected to restored as quickly and safely as possible, and as pipelines and infrastructure permit. The Constitution SPAR facility serves as a hub for the Constitution field, Ticonderoga field and the currently under development, Caesar field.
|
|
|
|
Caesar / Tonga Complex
Type: Development Activity
May. 2008 - Development on the Caesar / Tonga complex are still underway. Detailed reservoir simulation and subsea concept-validation work occurred in the 1st qtr. Unitization discussions were initiated with agreement that a phase development to the Constitution spar is the preferred option.
|
|
|
|
Increased Production expected at Ticonderoga
Type: Status Update
Apr. 2008 - Connection of GC768 #3 & #1ST4 wells to the Constitution facility is currently in progress. These wells were brought online in the 1st quarter of 2008.
|
|
|
|
Anadarko to Begin Booking Reserves for Jubilee and Tonga West
Type: Status Update
Mar. 2008 - Anadarko Petroleum announced that it expects to sanction and begin booking reserves associated with two of its substantial deepwater discoveries -- the Jubilee field offshore Ghana and Tonga West in the Gulf of Mexico -- in 2008. Anadarko anticipates each field to begin production as early as 2010.
|
|
|
|
Anadarko Strikes Oil at Tonga West
Type: New Discovery
Dec. 2007 - Anadarko has made an oil discovery at its West Tonga prospect on Green Canyon block 726 in the deepwater Gulf of Mexico.
|
|
|
|
Caesar Development Update
Type: Status Update
Nov. 2007 - The Caesar partnership formed an Integrated Project Team to study the development of the Caesar-Tonga discoveries as subsea tie-backs to the Constitution spar. The team is conducting studies to define the requirement of the subsea system for producing high-pressure oil and is creating subsurface models to optimize efficient recovery of both oil and gas. These studies will define the development plan for the field. Full project sanction is anticipated by the second half of 2008.
|
|
|
|
Anadarko Adds US GOM Properties
Type: Status Update
Nov. 2006 - The transaction with Chevron involves a swap of Anadarko's interests in the Mackenzie Delta, Beaufort Sea and Yukon areas in return for an incremental 12.5 percent working interest in seven deepwater Gulf of Mexico blocks encompassing the Tonga discovery, as well as enhanced terms within the companies' recently announced west Texas exploration joint venture. Anadarko, which currently is drilling an offset well to the Tonga discovery, now has a 37.5 percent working interest and intends to accelerate development of the field, potentially as a tie-back to the company's 100 percent owned Constitution production facility.
|
|
|
|
Kerr-McGee Makes Back-to-Back Deepwater Discoveries
Type: New Discovery
Jul. 2006 - Kerr-McGee has made another discovery in the deepwater Gulf of Mexico at the Caesar prospect. The Caesar #1 well, located in Green Canyon block 683 was drilled to a total depth of 29,721 feet and encountered quality oil pay. The Caesar discovery follows Kerr-McGee's recent announcement of a natural gas discovery at the deepwater Claymore prospect in Atwater Valley block 140.
|
|
|
|
Enterprise Reports Initial Flows on Constitution Pipelines
Type: Operator Update
Apr. 2006 - Enterprise Products Partners said Wednesday that it has received initial flows of crude oil and natural gas into its Constitution oil and natural gas pipelines from the Constitution and Ticonderoga fields in the Gulf of Mexico.
|
|
|
|
Kerr-McGee Begins Production at Deepwater Constitution Field
Type: Production Start
Mar. 2006 - Kerr-McGee reports that its 100%-owned Constitution field in the deepwater Gulf of Mexico achieved initial production on March 27, 2006 from the field's first dry-tree well.
|
|
|
|
Kerr-McGee Begins Production at Deepwater Constitution Field
Type: Production Start
Mar. 2006 - Kerr-McGee reports that its 100%-owned Constitution field in the deepwater Gulf of Mexico achieved initial production on March 27, 2006 from the field's first dry-tree well.
|
|
|
|
Kerr-McGee Turns on the Taps at Ticonderoga Field Early
Type: Production Start
Feb. 2006 - Kerr-McGee says the Ticonderoga field in the deepwater Gulf of Mexico achieved first production on Feb. 16, nearly two months ahead of schedule. Ticonderoga, located on Green Canyon block 768 in 5,250 feet of water, consists of two subsea wells tied back to Kerr-McGee's 100%-owned Constitution spar located on Green Canyon block 680. Kerr-McGee operates Ticonderoga with a 50% working interest. Noble Energy owns the remaining 50% working interest.
|
|
|
|
Anadarko Enters Participation Agreement in Deepwater Gulf of Mexico
Type: Appraisal Operations
Aug. 2005 - Anadarko Petroleum has signed an agreement with Chevron to participate in drilling four deepwater Gulf of Mexico prospects. Under this agreement, Anadarko will pay a disproportionate share of the drilling costs to earn a 20 to 25 percent working interest in two appraisal wells and two exploration wells scheduled to be completed by mid-year 2006. Anadarko will also gain rights in 29 deepwater Gulf of Mexico.
|
|
|
|
Technip Wins Work from Kerr-McGee for the Ticonderoga Field
Type: Contract Award
Jan. 2005 - Technip has been awarded the Ticonderoga subsea flowline installation contract by Kerr-McGee Oil. The Ticonderoga production will be tied back to Kerr-McGee's 100% owned Constitution Spar.
|
|
|
|
Constitution Field to Provide Oil for Cameron Hwy Pipeline
Type: Operator Update
Jul. 2004 - Cameron Highway Oil Pipeline Company has executed an
agreement with Kerr-McGee, for the dedication and movement of crude oil production from the Constitution and Ticonderoga fields, along with other future potential production from several undeveloped blocks in the south Green Canyon area of the deepwater trend of the Gulf of Mexico.
|
|
|
|
Kerr-McGee's Deepwater Success Continues with Ticonderoga
Type: New Discovery
Apr. 2004 - Kerr-McGee continues its success in the deepwater Gulf of Mexico with the Ticonderoga discovery well and initial sidetrack which encountered more than 250 feet of net high-quality hydrocarbon pay, primarily oil, in three zones. Kerr-McGee estimates that Ticonderoga, located on Green Canyon Block 768 in approximately 5,250 feet of water, offers potential resources of 30 million to 50 million barrels of oil equivalent. Operated by Kerr-McGee with 50% interest, Ticonderoga could be developed as a subsea tieback to the company's 100%-owned Constitution truss spar facility that will be located five miles to the north. Noble Energy owns the remaining 50% interest.
|
|
|
|
Mustang Wins Engineering Contract from Kerr-McGee
Type: Contract Award
Mar. 2004 - Mustang Engineering has been selected by Kerr-McGee to provide engineering, procurement services and project management assistance for the topsides production facility on a truss spar for its recently announced Constitution field.
|
|
|
|
Technip Wins Spar Contract for Kerr-McGee's Constitution Fld
Type: Facility Construction
Feb. 2004 - Technip has been awarded a contract by Kerr-McGee for the engineering and construction of a spar floating production platform hull and the engineering and delivery of the associated moorings and production riser system for the Constitution field in the Gulf of Mexico.
|
|
|
|
Gulf Island to Build Topside for Constitution Project
Type: Facility Construction
Feb. 2004 - Gulf Island Fabrication has executed a Letter of Intent with Kerr-McGee Oil & Gas Corp. to fabricate the topside for the Constitution truss spar platform.
|
|
|
|
Kerr-McGee to use a Truss Spar for Constitution Development
Type: Operator Update
Jan. 2004 - Kerr-McGee will develop its Constitution Field utilizing a truss spar faciilty. The field is located in the Gulf of Mexico in Green Canyon Blocks 679 and 680 in approximately 5,000 feet of water.
|
|
|
|
Schlumberger & ChevronTexaco Set New Gulf of Mexico Record
Type: Status Update
Dec. 2003 - Schlumberger Oilfield Services and ChevronTexaco have set new measurement-while-drilling (MWD) and logging-while-drilling (LWD) depth and pressure records for the Gulf of Mexico. These results were recorded while drilling the ChevronTexaco deepwater Tonga Exploratory Prospect located in Green Canyon Block 727.
|
|
|
|
Kerr-McGee Continues Deepwater Success
Type: New Discovery
Apr. 2003 - Kerr-McGee reports that recent appraisal drilling has confirmed the Constitution field in the deepwater Gulf of Mexico. Constitution, located in 5,000 feet of water on Green Canyon block 680, was drilled by the semisub, Noble Amos Runner, and is owned 100% by Kerr-McGee.
|
|
|
Constitution Truss Spar
|
|
Producing - Mar 27, 2006 to -
|
|
|
Ticonderoga
|
|
Producing - Feb 16, 2006 to -
Ticonderoga has an estimated resource range of 30 million to 50 million barrels of oil equivalent and has reached peak production volumes of approximately 20 thousand barrels of oil per day and 15 million cubic feet of natural gas per day.
|
|
Under Development - Aug 2005 to Feb 2006
Ticonderoga will be tied back to the Constitution Spar located on GC 679 & 680.
|
|
Discovery (Appraised) - Nov 2004 to Aug 2005
|
|
Appraisal Drilling - Aug 2004 to Nov 2004
|
|
Discovery (Drilled) - Apr 2004 to Aug 2004
Currently, the company is performing reservoir modeling, with plans to carryout additional appraisal work this year.
|
|
Exploratory Drilling - Mar 2004 to Apr 2004
Discovery drilled on GC768 using Noble's Amos Runner to a total depth of 13,556 feet and encountered more than 250 feet of net high-quality hydrocarbon pay, primarily oil in three zones.
|
|
|
Tonga
|
|
Producing - Mar 07, 2012 to -
|
|
Under Development - Apr 2009 to Mar 06, 2012
Joint development w/Caesar and Tonga West fields to be tied back to the Constitution Spar.
|
|
Discovery (Drilled) - Nov 2003 to Apr 2009
GC727 well being abandoned and held for future development
|
|
Exploratory Drilling - Jul 2003 to Nov 2003
GC 727 was drilled using Transocean's Discoverer Deep Seas.
|
|
|
Tonga West
|
|
Producing - Mar 07, 2012 to -
|
|
Under Development - Nov 2008 to Mar 06, 2012
Anadarko anticipates Tonga West to begin production to start as early as 2010.
|
|
Appraisal Drilling - Jul 2008 to Nov 2008
Transocean's Discoverer Spirit drilled appraisal well GC726 #1 (BH-GC770)
|
|
Discovery (Drilled) - Dec 17, 2007 to Mar 2008
Anadarko makes discovery at its Tonga West prospect on GC 726 using Diamond's Ocean Valiant.
|
|
Exploratory Drilling - Jun 18, 2007 to Dec 16, 2007
Anadarko makes discovery at its Tonga West prospect on GC 726 using Diamond's Ocean Valiant.
|
|
Bright Spot - Jul 01, 2002 to Jun 2007
Lease Date 7/1/2002; Lease Expiration 6/30/2012
|
|
|
Constitution
|
|
Producing - Mar 27, 2006 to -
The Constitution field is being developed with six dry-tree wells which will be processed through the Constitution truss spar facility located in GC680.
|
|
Under Development - May 2004 to Mar 2006
|
|
Appraisal Drilling - Mar 2003 to May 2004
Several appraisal wells were drilled during this period.
|
|
Discovery (Drilled) - Nov 2001 to Mar 2003
GC680 was temporarily abandoned.
|
|
Exploratory Drilling - Sep 2001 to Oct 2001
Green Canyon 680 was drilled to a total depth of 13727 feet.
|
|
|
Caesar
|
|
Producing - Under Dev. - Mar 07, 2012 to -
Anadarko Petroleum Corporation, as operator, announced first production at the Caesar/Tonga development in the Green Canyon area of the deepwater Gulf of Mexico. Production from Caesar/Tonga, with an estimated resource base of 200 to 400 million barrels of oil equivalent (BOE), is expected to ramp up to approximately 45,000 BOE per day from the first three subsea wells. A fourth development well is expected to be drilled and completed later this year, as part of the planned Phase I development.
|
|
Under Development - 2007 to Mar 11, 2012
|
|
Discovery (Drilled) - Aug 2006 to 2006
"We plan to immediately core the productive interval, then side-track the well approximately 4,000 feet to the north of the discovery to better determine the potential resources," added Hager. "Development options will be evaluated and could include a subsea tieback to our 100%-owned Constitution spar, just nine miles to the west in Green Canyon block 680."
|
|
Exploratory Drilling - Jan 2006 to Aug 2006
Discovery well drilled in GC 683 using Noble's Amos Runner. The No. 1 well was drilled to a total depth of 29,721 ft and encountered oil pays.
|
|
Bright Spot - May 01, 1997 to Jan 2006
Shell Offshore picked up GC683 at the MMS Central GOM Lease Sale #166 on 3/5/1997 with a bid of 757100.00; Lease expires 4/30/2007.
|
|
|
|
The SubseaIQ Team works everyday to provide you with the latest information on the offshore field development market.
The following table provides you with a detailed record of each addition and update made to this project by the SubseaIQ team.
|
| UPDATE TYPE |
DATE |
DAYS AGO |
| Field Status Updated |
Mar 12, 2012 |
432 |
|
| Field Status Added |
Mar 12, 2012 |
432 |
|
| Field Updated |
Mar 12, 2012 |
432 |
|
| Project Description Updated |
Mar 12, 2012 |
432 |
|
| Facility Updated |
Mar 12, 2012 |
432 |
|
| Activity Added |
Mar 12, 2012 |
432 |
|
| Project Description Updated |
May 05, 2011 |
744 |
|
| Project Description Updated |
Feb 24, 2011 |
814 |
|
| Field Updated |
Jan 31, 2011 |
838 |
|
| Activity Added |
Jan 31, 2011 |
838 |
|
| Field Updated |
Mar 05, 2010 |
1170 |
|
| Activity Added |
Mar 05, 2010 |
1170 |
|
| Field Updated |
Dec 31, 2009 |
1234 |
|
| Activity Added |
Nov 10, 2009 |
1285 |
|
| Field Updated |
Nov 09, 2009 |
1286 |
|
| Facility Updated |
Nov 09, 2009 |
1286 |
|
| Activity Added |
Nov 09, 2009 |
1286 |
|
| Field Updated |
Nov 03, 2009 |
1292 |
|
| Activity Added |
Nov 03, 2009 |
1292 |
|
| Field Updated |
Nov 02, 2009 |
1293 |
|
| Activity Added |
Nov 02, 2009 |
1293 |
|
| Field Updated |
Oct 06, 2009 |
1320 |
|
| Activity Added |
Oct 06, 2009 |
1320 |
|
| Field Updated |
Aug 04, 2009 |
1383 |
|
| Activity Added |
Aug 04, 2009 |
1383 |
|
| Field Updated |
Jul 20, 2009 |
1398 |
|
| Activity Added |
Jul 20, 2009 |
1398 |
|
| Activity Added |
Jul 17, 2009 |
1401 |
|
| Field Updated |
Jul 17, 2009 |
1401 |
|
| Facility Updated |
Jul 17, 2009 |
1401 |
|
| Field Updated |
Jul 08, 2009 |
1410 |
|
| Field Updated |
Jun 15, 2009 |
1433 |
|
| Field Updated |
May 18, 2009 |
1461 |
|
| Field Updated |
Apr 02, 2009 |
1507 |
|
| Activity Added |
Apr 02, 2009 |
1507 |
|
| Field Status Added |
Apr 02, 2009 |
1507 |
|
| Facility Updated |
Apr 02, 2009 |
1507 |
|
| Field Status Added |
Feb 03, 2009 |
1565 |
|
| Field Updated |
Feb 03, 2009 |
1565 |
|
| Activity Added |
Feb 02, 2009 |
1566 |
|
| Field Updated |
Dec 01, 2008 |
1629 |
|
| Project Description Added |
Nov 24, 2008 |
1636 |
|
| Activity Added |
Sep 22, 2008 |
1699 |
|
| Field Status Added |
Aug 18, 2008 |
1734 |
|
| Field Status Added |
May 29, 2008 |
1815 |
|
| Activity Added |
May 14, 2008 |
1830 |
|
| Activity Added |
Apr 22, 2008 |
1852 |
|
| Activity Added |
Mar 25, 2008 |
1880 |
|
| Field Status Added |
Mar 18, 2008 |
1887 |
|
| Field Status Added |
Feb 28, 2008 |
1906 |
|
| Field Added |
Feb 28, 2008 |
1906 |
|
| Field Status Added |
Feb 27, 2008 |
1907 |
|
| Field Status Added |
Feb 25, 2008 |
1909 |
|
| Field Status Added |
Feb 14, 2008 |
1920 |
|
| Field Status Added |
Jan 03, 2008 |
1962 |
|
| Field Added |
Jan 03, 2008 |
1962 |
|
| Field Added |
Dec 25, 2007 |
1971 |
|
| Field Status Added |
Dec 25, 2007 |
1971 |
|
| Field Status Added |
Dec 20, 2007 |
1976 |
|
| Facility Status Added |
Dec 20, 2007 |
1976 |
|
| Facility Added |
Dec 20, 2007 |
1976 |
|
| Field Added |
Dec 20, 2007 |
1976 |
|
| Field Added |
Dec 04, 2007 |
1992 |
|
| Activity Added |
Dec 04, 2007 |
1992 |
|
| Field Status Added |
Dec 04, 2007 |
1992 |
|
| Activity Added |
Nov 05, 2007 |
2021 |
|
| Activity Added |
Nov 02, 2006 |
2389 |
|
| Activity Added |
Jul 18, 2006 |
2496 |
|
| Activity Added |
Apr 12, 2006 |
2593 |
|
| Activity Added |
Mar 30, 2006 |
2606 |
|
| Activity Added |
Feb 21, 2006 |
2643 |
|
| Activity Added |
Aug 17, 2005 |
2831 |
|
| Activity Added |
Jan 21, 2005 |
3039 |
|
| Activity Added |
Jul 16, 2004 |
3228 |
|
| Activity Added |
Apr 19, 2004 |
3316 |
|
| Activity Added |
Mar 08, 2004 |
3358 |
|
| Activity Added |
Feb 25, 2004 |
3370 |
|
| Activity Added |
Feb 19, 2004 |
3376 |
|
| Activity Added |
Jan 14, 2004 |
3412 |
|
| Activity Added |
Dec 15, 2003 |
3442 |
|
| Activity Added |
Apr 22, 2003 |
3679 |
|
Project Update History Search - View all the lastest updates made by the SubseaIQ team.
|
|
| Facility Name |
Constitution Truss Spar |
|
| Duty |
Oil/Gas |
|
| Operator |
Anadarko |
|
| Current Status |
Producing since 2006 |
|
| Host Type |
SPAR |
|
| Water Depth |
1,554 m / 5,128 ft |
|
| Dev.Cost |
$600,000,000 |
| |
| Region |
US |
| |
| Location |
Green Canyon 680 |
| Field Name |
Tonga West |
|
| Discovery Date |
Dec 2007 |
|
| Block |
Green Canyon 726 |
|
| Reserve Type |
Oil |
|
| Current Status |
Producing |
|
| Production Start |
Mar 2012 |
|
| Water Depth |
1,433 m / 4,729 ft |
| Field Name |
Constitution |
|
| Discovery Date |
Oct 2001 |
|
| Block |
Green Canyon 680 |
|
| Reserve Type |
Oil/Gas |
|
| Current Status |
Producing |
|
| Production Start |
Mar 2006 |
|
| Water Depth |
1,554 m / 5,128 ft |
| Field Name |
Caesar |
|
| Discovery Date |
Aug 2006 |
|
| Block |
Green Canyon 683 |
|
| Reserve Type |
Oil/Gas |
|
| Current Status |
Producing - Under Dev. |
|
| Production Start |
|
|
| Water Depth |
1,372 m / 4,528 ft |
| Field Name |
Ticonderoga |
|
| Discovery Date |
Apr 2004 |
|
| Block |
Green Canyon 768 |
|
| Reserve Type |
Oil/Gas |
|
| Current Status |
Producing |
|
| Production Start |
Feb 2006 |
|
| Water Depth |
1,600 m / 5,280 ft |
| Field Name |
Tonga |
|
| Discovery Date |
Nov 2003 |
|
| Block |
Green Canyon 727/728 |
|
| Reserve Type |
Oil |
|
| Current Status |
Producing |
|
| Production Start |
Mar 2012 |
|
| Water Depth |
1,430 m / 4,719 ft |
|