| Operator: | BowLeven |
| Water Depth: | 70 m / 231 ft |
| Region: | Africa - West |
| Country: | Cameroon |
| Last Updated: | Apr 19, 2013 (view update history) |
|
The Etinde Permit area covers 1,439 square miles and comprises three shallow water blocks (MLHP-5,6 and 7) offshore Cameroon and covers portions of the Rio Del Rey and Douala Basins, both of which have proven petroleum systems and discovered hydrocarbon resources. The Etinde PSC was signed on 22 December 2008 and includes a three year exploration permit.
An exploitation authorization application was filed with Cameroon authorities in September 2012.
After several successful exploration and appraisal wells, it is envisioned that Etinde will be developed using the hub and spoke concept. The fields on block MLHP-7 are expected to be key contributors to proposed phase one development plans. It is envisaged that block MLHP-5 will be the focus for the second phase of development.
The Etinde Permit area covers 1,439 square miles and comprises three shallow water blocks (MLHP-5,6 and 7) offshore Cameroon and covers portions of the Rio Del Rey and Douala Basins, both of which have proven petroleum systems and discovered hydrocarbon resources. The Etinde PSC was signed on 22 December 2008 and includes a three year exploration permit.
An exploitation authorization application was filed with Cameroon authorities in September 2012.
After several successful exploration and appraisal wells, it is envisioned that Etinde will be developed using the hub and spoke concept. The fields on block MLHP-7 are expected to be key contributors to proposed phase one development plans. It is envisaged that block MLHP-5 will be the focus for the second phase of development.
|
|
|
Bowleven Completes IM-5 Testing
Type: Appraisal Operations
Apr. 2013 - Bowleven released the final updated on the IM-5 appraisal/development well offshore Cameroon. A drill stem test (DST) has been performed on the Intra Isongo reservoir which marks the end of the successful drilling and testing program. The Intra Isongo test achieved a flow rate of 37 MMscfd and 4,4664 bcpd through a 64/64-inch choke from a 95-foot perforated interval. Intra Isongo results combined with Middle Isongo delivered a maximum flow rate of 60 MMcfd and 7,819 bcpd. The IM-5 well will now be suspended as a future producer.
|
|
|
|
Bowleven Announces IM-5 DST Results
Type: Operator Update
Apr. 2013 - Bowleven announced the preliminary results from the IM-5 drill stem test (DST) in the MLHP-7 block off the coast of Cameroon. Flow rates of condensate-rich gas achieved 23 Mmscfd and 3,155 bcpd from the Middle Isongo reservoir. Preparations are now underway to test the Intra Isongo interal. Upon completion of the second DST the well will be suspended for use as a development well. IM-5 was drilled to 11,253 feet in 183 feet of water by the Atwood Aurora (350' ILC).
|
|
|
|
Bowleven Provides IM-5 Appraisal Update
Type: Drilling Operations
Feb. 2013 - Bowleven announced drilling operations at the IM-5 appraisal/development well have reached a depth of 10,925 feet which is just above the Middle Isongo reservoir. Moving forward, the reservoir will be cored and then drilling will resume to the target depth of 11,400 feet. Preliminary LWD results indicate the intersection of 262 gross feet of reservoir which corresponds to pre-drill seismic data. Additional logging to assess reservoir quality will take place once total depth has been reached. Additionally, the well intersected 104 feet of high quality Upper Isongo sands which proved to be water-bearing, as predicted.
|
|
|
|
Bowleven Updates Etinde
Type: Drilling Operations
Sep. 2012 - Bowleven's latest Etinde appraisal and development well offshore Cameroon is now underway. The IM-5 well is being drilled by the Atwood Aurora (350' ILC) in block MLHP-7. The primary objective of the operation is to establish reservoir and fluid properties in the Middle Isongo sands. An extensive logging, testing and coring suite will be performed as well. The well has been designed in a manner that will allow for use as a future producer. A second well will be drilled on the permit, the location of which will be determined by results of the IM-5.
|
|
|
|
Bowleven to Start Drilling Program Offshore Cameroon in 2Q10
Type: Appraisal Operations
Jan. 2010 - Bowleven plans to commence a drilling program on the Etinde Permit in April or May 2010, with the spudding of the IE appraisal well (IE-3) followed by the MLHP-5 exploratory well - a letter of intent has been issued for a rig to carry out the drilling activities. On the seismic front, the company signed a letter of intent for a vessel to acquire 3D marine seismic on the Etinde Permit. The parameters of a potential well, IF-2 (which would be the third well in this particular drilling program), depend on the results of seismic activity in the MLHP-7 Block. The Etinde permit area compromises three shallow water blocks, MLHP-5, MLHP-6 and MLHP-7, located offshore Cameroon, West Africa. Since 2007, Bowleven has drilled four wells in the permit, and contingent discovered resources for the permit include 225 MMbbl and 1 Tcf.
|
|
|
MLHP-5
|
|
Bright Spot - 2008 to -
Drilling is expected to commence in 2012
|
|
|
MLHP-6
|
|
Bright Spot - 2008 to -
Drilling is expected to commence in 2012
|
|
|
MLHP-7
|
|
Discovery (Appraised) - 2010 to -
The IE-3 appraisal well encountered oil.
|
|
Discovery (Drilled) - 2007 to 2010
Well IE-2 successfully drilled in 2007.
|
|
Bright Spot - 2004 to 2006
Drilling expected to commence 2004.
|
|
|
|
The SubseaIQ Team works everyday to provide you with the latest information on the offshore field development market.
The following table provides you with a detailed record of each addition and update made to this project by the SubseaIQ team.
|
| UPDATE TYPE |
DATE |
DAYS AGO |
| Field Updated |
Apr 19, 2013 |
61 |
|
| Activity Added |
Apr 19, 2013 |
61 |
|
| Field Updated |
Apr 05, 2013 |
75 |
|
| Activity Added |
Apr 05, 2013 |
75 |
|
| Field Updated |
Feb 01, 2013 |
138 |
|
| Activity Added |
Feb 01, 2013 |
138 |
|
| Project Description Added |
Sep 19, 2012 |
273 |
|
| Field Updated |
Sep 19, 2012 |
273 |
|
| Field Status Updated |
Sep 19, 2012 |
273 |
|
| Field Status Added |
Sep 19, 2012 |
273 |
|
| Activity Added |
Sep 19, 2012 |
273 |
|
| Field Updated |
Sep 18, 2012 |
274 |
|
| Field Status Updated |
Sep 18, 2012 |
274 |
|
| Field Updated |
Dec 13, 2011 |
554 |
|
| Field Status Updated |
Dec 13, 2011 |
554 |
|
| Field Status Added |
Feb 24, 2010 |
1211 |
|
| Field Updated |
Jan 25, 2010 |
1241 |
|
| Field Status Added |
Jan 25, 2010 |
1241 |
|
| Field Status Updated |
Jan 25, 2010 |
1241 |
|
| Field Added |
Jan 25, 2010 |
1241 |
|
| Activity Added |
Jan 25, 2010 |
1241 |
|
Project Update History Search - View all the lastest updates made by the SubseaIQ team.
|
|
| Field Name |
MLHP-5 |
|
| Discovery Date |
|
|
| Block |
MLHP-5, Etinde Permit |
|
| Reserve Type |
n/a |
|
| Current Status |
Bright Spot |
|
| Production Start |
|
|
| Water Depth |
70 m / 231 ft |
| Field Name |
MLHP-6 |
|
| Discovery Date |
|
|
| Block |
MLHP-6, Etinde Permit |
|
| Reserve Type |
n/a |
|
| Current Status |
Bright Spot |
|
| Production Start |
|
|
| Water Depth |
70 m / 231 ft |
| Field Name |
MLHP-7 |
|
| Discovery Date |
Jan 2007 |
|
| Block |
MLHP-7, Etinde Permit |
|
| Reserve Type |
Gas |
|
| Current Status |
Discovery (Appraised) |
|
| Production Start |
|
|
| Water Depth |
70 m / 231 ft |
|