| Operator: | DNO |
| Water Depth: | 90 m / 297 ft |
| Region: | MidEast - Persian Gulf |
| Country: | Oman |
| Last Updated: | Nov 2, 2012 (view update history) |
|
Block 8 offshore Oman covers an area of 104,526 acres (423 square kilometres) and contains the Bukha gas condensate field and the West Bukha oil and gas field.
Both fields provide a significant increase in current production levels for the Middle East.
Bukha
Discovered in 1979 by Elf, Bukha was developed in 1994 and commenced production later that year. Rak Petroleum serves as the operator and holds a 50% interest; LG International Corporation holds the remaining 50%.
The field development of Bukha consists of one well tied-back to a fixed platform situated in 295 feet (90 meters) of water. The field has a life expectancy of 15 years, and produces 28 MMcf/d (.79 MMcm/d) and 5,000 to 10,000 bpd of ...
Block 8 offshore Oman covers an area of 104,526 acres (423 square kilometres) and contains the Bukha gas condensate field and the West Bukha oil and gas field.
Both fields provide a significant increase in current production levels for the Middle East.
Bukha
Discovered in 1979 by Elf, Bukha was developed in 1994 and commenced production later that year. Rak Petroleum serves as the operator and holds a 50% interest; LG International Corporation holds the remaining 50%.
The field development of Bukha consists of one well tied-back to a fixed platform situated in 295 feet (90 meters) of water. The field has a life expectancy of 15 years, and produces 28 MMcf/d (.79 MMcm/d) and 5,000 to 10,000 bpd of condensate.
West Bukha
The West Bukha oil and gas field straddles the boundary between Oman and the Islamic Republic of Iran. Rak Petroleum, which holds a 50% interest, operates the field; LG International holds the remaining 50% interest.
The field was discovered in 1976 but was believed to be a gas condensate field and was abandoned shortly after. Then in 2006, Rak began exploring and drilling for new appraisal wells, including an extended horizontal section. The appraisal well, West Bukha-2, tested at a rate of 12,750 bopd and 26 MMcf/d (.73 MMcm/d) from the Mishiff-Maudud and Thamama reservoirs. The testing demonstrated that West Bukha could be developed by a stand-alone facility instead of tying the field back to Bukha.
Two years later, the Offshore Courageous jackup was contracted to deepen the West Bukha-2 well and also to drill the West Bukha-3 and West Bukha-4 wells, which were plugged and abandoned. Following the completion of appraisal drilling, the West Bukha wellhead platform was constructed and installed on the field.
West Bukha's field development consists of two wells tied-back to the six-slot unmanned West Bukha fixed platform located in 295 feet (90 meters) of water. Production is then tied through a subsea 12-inch-diameter multiphase flowline to the Bukha platform.
The West Bukha field commenced production on Feb. 18, 2009 and flows at a rate of 10,000 bopd and 30 MMcf/d (.84 MMcm/d).
Production
Production from both fields is sent through a 16-inch-diameter, 21-mile (33-kilometer) multiphase flowline to shore for processing at the Khor Khwair plant in the Emirate of Ras Al Khaimah.
|
|
|
DNO Might Double Output at West Bukha
Type: Development Activity
Nov. 2012 - Norwegian oil and gas company DNO International announced test results of the recently completed West Bukha-4 well offshore the Sultanate of Oman. On a 54/64-inch choke, the well flowed 7,000 barrels of 39 degree API oil and 15 million cubic feet of gas per day through a test separator. Once the new well is on-line, production from the West Bukha field is expected to achieve 15,000 barrels per day which almost doubles the current rate. Boasting a total depth of nearly 19,700 feet, the well has the longest reach of any drilled well in Oman's waters. West Bukha-4 targeted a previously un-drilled zone and is the second of a three well Block 8 drilling campaign initiated last year.
|
|
|
|
DNO Completes Drilling of West Burkha-5 Well in Oman
Type: Development Activity
Jul. 2012 - DNO International has completed the drilling of the West Bukha-5 well in Block 8 and is preparing to resume operations at the West Bukha-4 well, whose top-hole section was previously drilled. Results from the initial flow test of West Bukha-5 confirm the presence of oil in the Thamama reservoir, with an estimated flow capacity of 1,500-2,000 barrels per day. Samples and measurements taken during the initial test flow period indicate an oil gravity of 35-degree API and a gas-to-oil ratio of 5,000 standard cubic feet/barrel. The well will be put on production this summer once normal offshore pipeline operations resume. West Bukha-5 is the first of a three-well development drilling campaign in Block 8. Drilled to a total depth of 17,060 feet (5,1200 meters), including a 3,000-feet (914-meter) horizontal section with good fracture indications, West Bukha-5 is the deepest well yet for the company in Oman.
|
|
|
|
RAK to Start Multi-Well Drilling Campaign this summer
Type: Status Update
May. 2011 - RAK Petroleum plans to commence a multi-well drilling program in June 2011 and continue through the summer of 2012. The drilling program includes three development wells on the Bukha and West Bukha fields in Block 8 offshore Oman; and deepening of an existing well on the Saleh field offshore Ras Al Khaimah as a first step towards full field redevelopment. RAK holds a 50% operating interest in Block 8 and 100% interest in the Saleh field.
|
|
|
|
RAK Acquires Eagle Energy, Increases Interest in West Bukha Field
Type: Operator Update
Apr. 2009 - RAK purchased Eagle Energy, a wholly-owned subsidiary of UK-based Heritage Oil Limited, for $28 million. Eagle holds a 10% interest in Block 8 offshore Oman, bringing RAK's total interest to 50%. Block 8 includes the West Bukha field, as well as the Bukha field. West Bukha is developed through two subsea wells tied to a six-slot unmanned platform in 90 meters of water; production is then routed to the Bukha production platform nearby.
|
|
|
Bukha Platform
|
|
Producing - Feb 2009 to -
|
|
|
West Bukha Platform
|
|
Producing - Feb 01, 2009 to -
RAK Petroleum announced in February 2009 that first production from Block 8's West Bukha field located offshore in the Strait of Hormuz had commenced with initial capacity of 10,000 barrels per day of 42 degree API gravity oil and 30 million cubic feet per day of associated gas from two wells through a six-slot unmanned platform located in 90 meters of water some 25 kilometers from the Musandam Peninsula.
|
|
|
Bukha
|
|
Producing - Jan 2008 to -
|
|
Under Development - 1994 to Dec 2007
|
|
|
West Bukha
|
|
Producing - Feb 2009 to -
RAK Petroleum announced in February 2009 that first production from Block 8's West Bukha field located offshore in the Strait of Hormuz had commenced with initial capacity of 10,000 barrels per day of 42 degree API gravity oil and 30 million cubic feet per day of associated gas from two wells through a six-slot unmanned platform located in 90 meters of water some 25 kilometers from the Musandam Peninsula.
|
|
Appraisal Drilling - 2006 to Jan 2009
Between 2006 and 2008 drilling by RAK Petroleum of new appraisal wells, including an extended horizontal section, demonstrated significant oil productivity from the Mishriff-Maudud and Thamama reservoirs, leading to the recent completion of field development.
|
|
Discovery (Drilled) - 1976 to 1976
West Bukha was first discovered in 1976 but was believed to be a gas condensate field and abandoned as non-commercial.
|
|
|
|
The SubseaIQ Team works everyday to provide you with the latest information on the offshore field development market.
The following table provides you with a detailed record of each addition and update made to this project by the SubseaIQ team.
|
| UPDATE TYPE |
DATE |
DAYS AGO |
| Field Updated |
Nov 02, 2012 |
198 |
|
| Facility Updated |
Nov 02, 2012 |
198 |
|
| Activity Added |
Nov 01, 2012 |
199 |
|
| Field Updated |
Nov 01, 2012 |
199 |
|
| Field Updated |
Jul 18, 2012 |
305 |
|
| Facility Updated |
Jul 18, 2012 |
305 |
|
| Activity Added |
Jul 18, 2012 |
305 |
|
| Field Updated |
Feb 16, 2012 |
458 |
|
| Project Description Updated |
Jun 23, 2011 |
696 |
|
| Field Updated |
May 26, 2011 |
724 |
|
| Activity Added |
May 20, 2011 |
730 |
|
| Project Description Updated |
Feb 10, 2011 |
829 |
|
| Project Description Updated |
Mar 05, 2010 |
1171 |
|
| Project Description Updated |
Jul 27, 2009 |
1392 |
|
| Project Description Updated |
Jul 17, 2009 |
1402 |
|
| Project Description Added |
Apr 17, 2009 |
1493 |
|
| Field Updated |
Apr 16, 2009 |
1494 |
|
| Facility Added |
Apr 08, 2009 |
1502 |
|
| Facility Status Added |
Apr 08, 2009 |
1502 |
|
| Field Status Added |
Apr 08, 2009 |
1502 |
|
| Field Added |
Apr 08, 2009 |
1502 |
|
| Activity Added |
Apr 08, 2009 |
1502 |
|
Project Update History Search - View all the lastest updates made by the SubseaIQ team.
|
|
| Facility Name |
Bukha Platform |
|
| Duty |
Oil/Gas |
|
| Operator |
DNO |
|
| Current Status |
Producing since 2009 |
|
| Host Type |
Fixed Platform |
|
| Water Depth |
90 m / 297 ft |
|
| Dev.Cost |
n/a |
| |
| Region |
Oman |
| |
| Location |
Block 8 |
| Facility Name |
West Bukha Platform |
|
| Duty |
Gas |
|
| Operator |
DNO |
|
| Current Status |
Producing since 2009 |
|
| Host Type |
Fixed Platform |
|
| Water Depth |
90 m / 297 ft |
|
| Dev.Cost |
n/a |
| |
| Region |
Oman |
| |
| Location |
Block 8 |
| Field Name |
West Bukha |
|
| Discovery Date |
Jan 1976 |
|
| Block |
Block 8 |
|
| Reserve Type |
Oil/Gas |
|
| Current Status |
Producing |
|
| Production Start |
Feb 2009 |
|
| Water Depth |
90 m / 297 ft |
| Field Name |
Bukha |
|
| Discovery Date |
|
|
| Block |
Block 8 |
|
| Reserve Type |
Gas |
|
| Current Status |
Producing |
|
| Production Start |
Jan 2008 |
|
| Water Depth |
90 m / 297 ft |
|