| Gomez Hub |
 |
| Operator: | ATP |
| Water Depth: | 914 m / 3,016 ft |
| Region: | N. America - US GOM |
| Country: | US |
| Last Updated: | Aug 10, 2011 (view update history) |
|
Located in the deepwater Gulf of Mexico, the Gomez project consists of one field, Gomez, and three satellite fields, Anduin, Anduin West and Gladden. The four fields are tied-back to the ATP Innovator platform.
Gomez Field
Located on Mississippi Canyon Block 711, the Gomez field is situated in 3,000 feet (914 meters) of water in the Outer Continental Shelf of the Gulf of Mexico. Wholly owned and operated by ATP Oil and Gas, Gomez was acquired by the company in 2003.
In 1997, Union Pacific Resources drilled the Gomez discovery well, No.4 ST1; three years later a sidetrack well encountered 125 feet (38 meters) of oil and gas pay in a Lower Pliocene sand interval, but the well was not tested. When ATP acquired ownership of the lease, the No. 4 ...
Located in the deepwater Gulf of Mexico, the Gomez project consists of one field, Gomez, and three satellite fields, Anduin, Anduin West and Gladden. The four fields are tied-back to the ATP Innovator platform.
Gomez Field
Located on Mississippi Canyon Block 711, the Gomez field is situated in 3,000 feet (914 meters) of water in the Outer Continental Shelf of the Gulf of Mexico. Wholly owned and operated by ATP Oil and Gas, Gomez was acquired by the company in 2003.
In 1997, Union Pacific Resources drilled the Gomez discovery well, No.4 ST1; three years later a sidetrack well encountered 125 feet (38 meters) of oil and gas pay in a Lower Pliocene sand interval, but the well was not tested. When ATP acquired ownership of the lease, the No. 4 ST1 well was tested, and flowed at a rate of 13,610 bopd and 53 MMcf/d (1.5 MMcm/d).
Gomez contains an estimated 150 Bcf of proven and probable reserves.
Field Development
The Gomez field development consists of four subsea wells tied-back to the ATP Innovator platform, moored on Mississippi Canyon Block 711.
The Ocean Quest semisub developed the field during two phases. Under the first phase of the project, two wells came online, No. 4 ST1 and No. 6, which are located on the southern portion of the field. In Phase two of the project two additional wells, No. 5 and No. 7, came online from the northern portion of the project.
NKT Flexibles received a contract for the supply, design, test and the delivery of two dynamic risers -- a 6-inch-diameter oil export line and an 8-inch-diameter gas export line. Pegasus International provided the engineering and design for FEED, as well as the detailed design of the subsea wells, umbilicals, catenary risers, pipelines, the topside processing facilities, instruments, electrical, and controls.
ATP decided to convert a semisubmersible drilling rig, the Rowan Midland, into a floating production facility, the ATP Innovator, in order for the platform to process gas from the field's subsea wells. The facility is installed in 3,281 feet (1,000 meters) of water, and has the capacity to produce 20,000 bopd and 60 MMcf/d.
Oil and gas is transported via two, 28-mile-long (45-kilometer-long) pipelines to the sales point at Grand Isle 115.
Satellite Fields
Anduin
Anduin is located on Mississippi Canyon Block 755, in a water depth of 2,400 feet (732 meters). The field is wholly owned and operated by ATP Oil and Gas.
In 2005, the discovery well, MC 755 No. 2, encountered 48 feet (15 meters) of gross oil pay. When ATP acquired the lease in January 2007, the drilling rig encountered material logged hydrocarbons in both a down-dip and up-dip location. The field was developed as a subsea tie-back to the ATP Innovator.
The field has proven and probable reserves of 47 Bcf and commenced production in the fourth quarter of 2007.
Anduin West
The Anduin West field is located at Mississippi Canyon Block 754 in approximately 2,696 feet (822 meters) of water. Newfield owns a 50% working interest in Anduin West; ATP owns a 25% working interest; and LLOG Exploration owns the remaining 25% interest.
The discovery drilling of the Anduin West field encountered 30 feet (9 meters) of net gas and condensate pay. The well was completed by the Noble Max Smith semisub, and a production test was conducted in May 2008.
Development plans call for the field to be developed as a subsea tie-back to the ATP Innovator. The field commenced production in February 2011.
Gladden
Gladden is located on Mississippi Canyon Block 800, in a water depth of 3,116 feet (950 meters). Newfield serves as the operator and holds a 47.50% interest; Deep Gulf Energy holds 20%; Arena Exploration holds 12.50%; CL&F Resources holds 10%; and ATP Oil & Gas holds the remaining 10%.
The prospect was discovered in 2008 by Diamond Offshore's Ocean Quest, which found 80 feet (24 meters) of net oil pay. An up-dip location was drilled and completed in May 2008. Gladden was developed as a subsea tie-back to the ATP Innovator facility, and production commenced in the first quarter of 2011.
|
|
|
ATP Develops Sixth well at Gomez Hub
Type: Development Activity
Aug. 2011 - In June 2011, ATP O&G completed and returned to production the Missippi Canyon Block 711 No. 5 well, making it the six well to come online at Gomez. The DOCD (Development Drilling Plan) for MC Block 711 No. 9 and MC Block 711 No. 10 were submitted to the governmental agency, and upon approval, ATP expects to commence drilling on the wells with first production expected in mid-2012. The company also submitted an exploration plan for MC Block 710, a block adjacent to MC 711, which is believed to display similar seismic and technical characteristics to MC Block 711. Original proved reserve estimates of the Gomez Hub accounted for 14.8 MMboe, and since online, the Hub has produced gross volumes of 24.8 MMboe. Located in the deepwater Gulf of Mexico, the Gomez project consists of one field, Gomez, and three satellite fields, Anduin, Anduin West and Gladden. The four fields are tied-back to the ATP Innovator platform. ATP operates Gomez Hub, and has a 100% working interest in MC 711, 710 and 755; and a 75% working interest in MC 754.
|
|
|
|
ATP Updates Operations at Gomez Hub
Type: Status Update
Jun. 2010 - The MC 754 No. 1 well at the Gomez Hub was completed and will come online late 2010, following a pipeline lay and connection. Later in the year and in early 2011, two wells, MC 711 No. 9 and MC 700 No. 10, are scheduled for drilling and will then be connected to the platform for production. ATP operates the Gomez Hub with a 100% working interest at MC 711 and 755 and a 75% working interest at MC 754. Located in the deepwater Gulf of Mexico, the Gomez project consists of one field, Gomez, and three satellite fields, Anduin, Anduin West and Gladden. The four fields are tied-back to the ATP Innovator platform.
|
|
|
|
ArcLight Closes on Acquisition of Gomez Pipelines
Type: Subsea Equipment
Sep. 2009 - ArcLight has closed on its purchase from ATP of the oil and natural gas pipelines that service ATP's Gomez Hub located at Mississippi Canyon Block 711 in the deepwater Gulf of Mexico for $78 million. ArcLight established OIP to invest in critical pipeline, platform and production infrastructure assets in the Gulf of Mexico. "We are very pleased to have closed this important transaction with ATP to monetize their pipeline assets while providing ongoing gas gathering and oil export services from the Gomez Hub," said Robb Turner, senior partner at ArcLight. "OIP is actively evaluating further investments that bring needed capital into the Gulf," added Mr. Turner. The oil pipeline is 28 miles long and has the capacity to transport up to 25,000 barrels of oil per day to the Amberjack pipeline system.
|
|
|
|
ATP to Sell Gomez Pipelines in Deepwater GOM
Type: Status Update
Sep. 2009 - ATP has agreed to sell both the oil and natural gas pipelines that service ATP's Gomez Hub at Mississippi Canyon Block 711 in the Deepwater Gulf of Mexico to ArcLight Capital Partners, for $78 million. The oil pipeline is 28 miles long (45 kilometers long) and has the capacity to transport up to 25 thousand barrels of oil per day to the Amberjack pipeline system. The gas pipeline, 28 miles long (45 kilometers long), has the capacity to transport 100 million cubic feet of natural gas to the Discovery Gas Pipeline. ATP will remain the operator of Mississippi Canyon Block 711 and will remain as operator of both pipelines.
|
|
|
|
ATP First in Gulf to Install ADS-B Air Traffic Control System
Type: Status Update
Jul. 2009 - ATP announced that the ATP Innovator is the first Gulf of Mexico offshore platform to install an Automatic Dependent Surveillance-Broadcast (ADS-B) system for air traffic control to and from platforms in the Gulf of Mexico. ATP partnered with the Federal Aviation Administration (FAA) Surveillance and Broadcast Services Office, the Helicopter Association International (HAI), Gulf helicopter operators, and other offshore oil and gas companies to implement this new technology. ADS-B uses precise location data from the global satellite network to provide real-time, radar-like traffic information directly to ADS-B equipped aircraft, then transmitted to shore to the FAA and to air traffic controllers and other aircraft. In addition, the system will provide helicopter operators in the Gulf immediate access to updated weather information and other flight information services. The system on the ATP Innovator platform will be part of a larger network of systems which are set to go operational in December 2009.
|
|
|
|
Newfield Preps for Production of Subsea Well at Gladden
Type: Status Update
Jul. 2009 - Newfield submitted a Development Operations Coordination Document to Minerals Management Service for the Gladden field. The document proposes to commence production of subsea well no. 001. Gladden is located in 3,116 feet (960 meters) of water on Mississippi Canyon Block 800 and was discovered in early 2008. Gladden is being developed as a subsea tie-back to the ATP Innovator at the Gomez Hub. Newfield is the operator of the Gladden field and holds a 47.5% interest. Other participants are Deep Gulf 20%, Arena Energy 12.5%, ATP 10% and CL&F 10%.
|
|
|
|
Anduin West & Gladden Fields Expected Production Start-up by Early 2010
Type: Status Update
Apr. 2009 - ATP Oil and Gas Corporation provided update on the Anduin West field located on Mississippi Canyon block 754 and the Gladden field on Mississippi Canyon block 800. The company expects production to start late in 2009 or early 2010. Both fields are subsea tiebacks to the ATP Innovator at the Gomez Hub.
|
|
|
|
ATP Secures Investment for Deepwater GOM Unit
Type: Operator Update
Feb. 2009 - GE Energy Financial Services agreed to invest $150 million in a partnership with ATP Oil & Gas which will own and operate a floating oil and gas production unit in deepwater Gulf of Mexico. GE Energy Financial Services will invest $150 million for a 49 percent limited partnership stake, its first investment in a floating oil and gas production facility. ATP Oil & Gas Corporation will hold the remaining 51 percent stake and will serve as managing partner.
|
|
|
|
Newfield Expects First Production at Gladden in Early 2010
Type: Status Update
Feb. 2009 - Newfield reported that the MC 800 #1 updip sidetrack tested approximately 5,600boepd and expects first production from the Gladden field in early 2010. Gladden was discovered in April 2008 and drilled by Diamond's Ocean Quest semisub rig. Gladden is operated by Newfield who holds a 75% interest in the field with ATP holding the remaining 25%.
|
|
|
|
Newfield Updates on its Anduin West Field
Type: Development Activity
Oct. 2008 - According to Newfield's 3rd Quarter Earnings call, the Anduin West field, located on Mississippi Canyon Block 754, is currently under development. First production is scheduled for the latter part of 2009.
|
|
|
|
ATP Establishes Partial Production From Gomez
Type: Status Update
Sep. 2008 - ATP has established partial production at Mississippi Canyon 711 (Gomez) after weathering both Hurricanes Gustav and Ike. Inspections confirmed very little physical damage to the facility.
|
|
|
|
Minimal Damage of ATP's Innovator at Gomez Hub
Type: Status Update
Sep. 2008 - ATP Oil & Gas reports minimal impact from Hurricane Ike based on preliminary inspections of its production and drilling operations in the Gulf of Mexico. The ATP Innovator at ATP's Mississippi Canyon Block 711 "Gomez" Hub is on location and initial assessments found minimal damage.
|
|
|
|
ATP's Innovator at "Gomez" Held Strong Through Hurricane Gustav
Type: Status Update
Sep. 2008 - ATP Oil & Gas says based on preliminary inspections of its production and drilling operations in the Gulf of Mexico, there was minimal impact from Hurricane Gustav. Gustav's path was about 12 miles east of the ATP Innovator, moored at ATP's Gomez Hub (Mississippi Canyon 711). The Innovator held position and initial assessments found no significant damage.
|
|
|
|
Newfield Encounters Oil at Gladden Prospect
Type: New Discovery
Apr. 2008 - The Gladden Prospect, located at Mississippi Canyon 800, found 80 feet of net oil pay. An updip location is being drilled that is expected to be completed in late May, 2008. The Company has production handling agreements in place with nearby host facilities and expects first production in late 2009
|
|
|
|
Newfield Logs Pay at Anduin West Prospect
Type: New Discovery
Apr. 2008 - The Anduin West Prospect found 30 feet of net gas and condensate pay. The well is being completed and a production test is planned in the next week. The Company has production handling agreements in place with nearby host facilities and expects first production from in late 2009.
|
|
|
|
ATP Completes Production Enhancement at Gomez
Type: Status Update
Oct. 2007 - ATP Oil & Gas has completed capacity upgrade and increased production at its 100%-owned and -operated Gomez development.
|
|
|
|
ATP Reports Q2 Results, Ops Update
Type: Status Update
Aug. 2007 - In the second half of 2008, the operator of MC 800 and MC 754 is planning to drill exploratory targets in these blocks. If successful, these exploratory targets will be brought on production through the ATP Innovator. ATP owns a 50% W.I. in MC 754 and a 25% W.I. in MC 800.
|
|
|
|
ATP Achieves Record Quarterly Net Income and Revenue
Type: Status Update
May. 2007 - Gomez Hub - Immediately following the acquisition of Anduin, ATP moved a semi-submersible drilling rig on location to reenter, sidetrack and complete the MC 755 #2 ST1 well. The operation was successful and the well will be tied back to the ATP Innovator and placed on production this summer.
|
|
|
|
ATP Innovator Becomes Deepwater Platform for Gomez Hub
Type: Status Update
Feb. 2007 - ATP Oil & Gas has named its floating offshore production platform the "ATP Innovator." The ATP Innovator, previously the Rowan Midland was a semisubmersible drilling rig acquired by ATP and strategically converted in a short period of time to a floating production platform for the hub development of all of the Gomez reservoirs.
|
|
|
|
ATP Reports Major Gomez Expansion
Type: Status Update
Jan. 2007 - ATP Oil & Gas Corporation on Wednesday announced a major expansion of interests and operations at Mississippi Canyon ("MC") 711 ("Gomez"), where ATP is presently producing greater than 100 MMcfe/d.
|
|
|
|
ATP Reports Major Gomez Expansion
Type: Acreage Acquisition
Jan. 2007 - ATP acquired interests in a package of properties including a 100% working interest in a successful discovery well in the northwest quarter of MC 755 ("Anduin") located in an adjacent block south of Gomez. The MC 755 #2 discovery well of Anduin was drilled in 2005 and encountered material logged hydrocarbons in both a down-dip and up-dip location. ATP intends to establish production at Anduin later this year by side tracking and completing the MC 755 #2 well and tying it back to ATP's floating production facility at MC 711.
|
|
|
|
Permanent SEPLA Mooring Unit Installed in Gulf
Type: Subsea Equipment
Apr. 2006 - InterMoor has successfully installed the world’s first permanent SEPLA mooring system for a floating production unit (FPU) in the Gulf of Mexico.<
|
|
|
|
ATP Marks First Production at Mississippi Canyon 711
Type: Production Start
Mar. 2006 - ATP Oil & Gas announced first production at its Mississippi Canyon 711 Gomez project. The second phase of development, scheduled for mid-2006, will include additional developmental drilling to more completely exploit the primary pay sands as well as the other oil and gas sands that have been identified at shallower depths.
|
|
|
|
ATP Marks First Production at Mississippi Canyon 711
Type: Production Start
Mar. 2006 - ATP Oil & Gas announced first production at its Mississippi Canyon 711 project in the Gulf of Mexico.
|
|
|
|
ATP Completes Well Work at Gomez Prospect
Type: Development Activity
Dec. 2005 - ATP has completed the well work at its Mississippi Canyon 711 (Gomez) project. The Ocean Voyager completed and made ready for production the first two wells in the first phase of development.
|
|
|
|
ATP to Acquire Rowan Midland for Gomez
Type: Status Update
Oct. 2005 - ATP Oil & Gas will acquire the Rowan Midland from Rowan Companies to serve as the floating offshore production platform for the area around ATP's Mississippi Canyon 711 development, Gomez. The the rig was previously committed under a lease, but acquiring the Midland gives ATP significant short term and longer term operating flexibility.
|
|
|
|
ATP to Acquire Rowan Midland for Gomez
Type: Facility Construction
Oct. 2005 - ATP Oil & Gas will acquire the Rowan Midland from Rowan Companies to serve as the floating offshore production platform for the area around ATP's Mississippi Canyon 711 development, Gomez.
|
|
|
|
ATP Mobilizes Rowan Midland for Mississippi Canyon 711 Project
Type: Status Update
Aug. 2005 - ATP has mobilized the Rowan Midland for its Mississippi Canyon 711 (Gomez) project. The Rowan Midland will serve as the mobile production platform at Gomez. Production facilities are near completion and are ready for installation on the Rowan Midland at the Sabine Pass yard.
|
|
|
|
Intermoor Wins Mooring Contract from ATP
Type: Facility Construction
Jun. 2005 - InterMoor has finalized an agreement with ATP Oil & Gas to anchor a Floating Production Unit (FPU) in the Gulf of Mexico's Mississippi Canyon 711 for ATP's Gomez project.
|
|
|
|
Newfield Announces Exploration Discoveries
Type: New Discovery
Feb. 2005 - Newfield also announced a deepwater discovery with the Anduin Prospect, located at Mississippi Canyon 755 in about 2,400' of water. The well found about 48' of gross oil pay. The partners are currently preparing to drill an updip sidetrack location. Information from the sidetrack will be used to determine Anduin's reserve size and development options. Two additional locations exist on Mississippi Canyon 755 and adjacent 754. Newfield owns a 50% non-operated interest in Anduin.
|
|
|
|
ATP Mississippi Canyon Well Test Successful at 134 Mmcfe/d
Type: Development Activity
Dec. 2004 - ATP tested its Mississippi Canyon 711 #4 ST1 well with a total test rate of 13,610 BOPD and 52.7 MMcf/d or 134 MMcfe/d. The multiple day flow test recorded flowing tubing pressures exceeding 3500 psi with very little reservoir drawdown. The MC 711 #4 ST1 well logged approximately 157 total net feet of oil and gas pay in Lower Pliocene sands.
|
|
|
|
ATP Begins Development Work at Mississippi Canyon 711
Type: Development Activity
Nov. 2004 - ATP Oil & Gas reports that the Noble Therald Martin is on location at Mississippi Canyon 711, also known as "Gomez".
The rig is scheduled to reenter, test, and complete the MC 711 No. 4 ST1
|
|
|
|
ATP Oil & Gas Acquires Gulf of Mexico Acreage
Type: Acreage Acquisition
Sep. 2003 - ATP Oil & Gas has acquired operatorship in Mississippi Canyon 711, an oil and gas discovery named "Gomez" located in approximately 3000 feet of water in the Gulf of Mexico.
|
|
|
Gladden
|
|
Producing - Feb 10, 2011 to -
|
|
Under Development - Aug 01, 2008 to Feb 09, 2011
|
|
Discovery (Appraised) - May 2008 to Jul 01, 2008
|
|
Appraisal Drilling - Apr 2008 to May 2008
MC 800 #1 drilled by the Ocean Quest encountered 80 feet of net oil pay. Currently drilling an updip location which is expected to be completed in May.
|
|
Exploratory Drilling - Feb 2008 to Apr 2008
Diamond's Ocean Quest is currently drilling exploratory well #1 on MC800.
|
|
Bright Spot - May 2005 to Feb 2008
Original Lease was held by Anadarko 7/1/1997. On 5/1/2005 Newfield acquired 100% of MC 800 and in April of 2007 ATP acquired 50% of Newfield's interest.
|
|
|
Gomez Hub (ATP Innovator)
|
|
Producing - Mar 10, 2006 to -
|
|
Under Construction - 2005 to 2005
Rowan Midland semisub undergoing conversion to ATP Innovator at Sabine Pass, Texas.
|
|
|
Anduin
|
|
Producing - Oct 2007 to -
|
|
Under Development - Mar 2007 to Sep 2007
MC755 #2 ST2 well tied-back to ATP Innovator Hub.
|
|
Appraisal Drilling - Jan 2007 to Mar 2007
MC 755 #2 ST2 drilled by Ocean Quest
|
|
Discovery (Drilled) - Mar 2005 to Jan 2007
|
|
Exploratory Drilling - Dec 2004 to Feb 2005
MC 755 drilled by GSF Celtic Sea
|
|
|
Anduin West
|
|
Producing - Feb 27, 2011 to -
|
|
Under Development - Jun 2008 to Feb 26, 2011
1st production expected early 2010.
|
|
Discovery (Drilled) - Apr 2008 to May 2008
The Anduin West Prospect found 30 feet of net gas and condensate pay. The well is being completed and a production test is planned in the next week.
|
|
Exploratory Drilling - Feb 2008 to Apr 2008
MC 754 #2 & #3 wells drilled by Noble Max Smith.
|
|
Bright Spot - Jun 2002 to Feb 2008
MC 754 acquired in Central GoM Lease Sale 182.
|
|
|
Gomez
|
|
Producing - Mar 10, 2006 to -
Two wells MC 711 #4 ST1 & #6 on production. The second phase of development, scheduled for mid-2006, will include additional developmental drilling to more completely exploit the primary pay sands as well as the other oil and gas sands that have been identified at shallower depths.
|
|
Under Development - Jan 2005 to 2005
Two wells have been completed and made ready for production.
|
|
Discovery (Appraised) - 2001 to 2004
Nov. 2004 Noble Therald Martin re-enters, tests & completes MC 711 #4 ST1.
|
|
Appraisal Drilling - 2000 to 2000
MC 711 #4 ST1 well confirms initial discovery.
|
|
Discovery (Drilled) - 1998 to 1999
|
|
Exploratory Drilling - 1997 to 1997
Initial discovery well drilled.
|
|
|
|
The SubseaIQ Team works everyday to provide you with the latest information on the offshore field development market.
The following table provides you with a detailed record of each addition and update made to this project by the SubseaIQ team.
|
| UPDATE TYPE |
DATE |
DAYS AGO |
| Field Updated |
Jul 25, 2012 |
303 |
|
| Field Status Updated |
Sep 02, 2011 |
630 |
|
| Field Status Added |
Sep 02, 2011 |
630 |
|
| Project Description Updated |
Sep 02, 2011 |
630 |
|
| Field Updated |
Aug 10, 2011 |
653 |
|
| Activity Added |
Aug 10, 2011 |
653 |
|
| Project Description Updated |
Jun 23, 2011 |
701 |
|
| Project Description Updated |
May 16, 2011 |
739 |
|
| Project Description Updated |
Apr 21, 2011 |
764 |
|
| Project Description Updated |
Apr 14, 2011 |
771 |
|
| Project Description Updated |
Mar 31, 2011 |
785 |
|
| Project Description Updated |
Feb 24, 2011 |
820 |
|
| Project Description Updated |
Feb 10, 2011 |
834 |
|
| Project Description Updated |
Aug 12, 2010 |
1016 |
|
| Activity Added |
Jun 04, 2010 |
1085 |
|
| Project Description Updated |
May 28, 2010 |
1092 |
|
| Project Description Updated |
Feb 08, 2010 |
1201 |
|
| Project Description Updated |
Jan 05, 2010 |
1235 |
|
| Field Updated |
Dec 10, 2009 |
1261 |
|
| Field Updated |
Nov 11, 2009 |
1290 |
|
| Field Updated |
Oct 08, 2009 |
1324 |
|
| Field Updated |
Sep 28, 2009 |
1334 |
|
| Facility Updated |
Sep 28, 2009 |
1334 |
|
| Activity Added |
Sep 28, 2009 |
1334 |
|
| Field Updated |
Sep 22, 2009 |
1340 |
|
| Facility Updated |
Sep 22, 2009 |
1340 |
|
| Activity Added |
Sep 22, 2009 |
1340 |
|
| Field Updated |
Sep 04, 2009 |
1358 |
|
| Field Updated |
Aug 03, 2009 |
1390 |
|
| Facility Updated |
Jul 28, 2009 |
1396 |
|
| Activity Added |
Jul 28, 2009 |
1396 |
|
| Activity Added |
Jul 27, 2009 |
1397 |
|
| Field Updated |
Jul 27, 2009 |
1397 |
|
| Field Updated |
Jun 19, 2009 |
1435 |
|
| Field Updated |
Jun 11, 2009 |
1443 |
|
| Field Updated |
Jun 03, 2009 |
1451 |
|
| Facility Updated |
Apr 27, 2009 |
1488 |
|
| Activity Added |
Apr 22, 2009 |
1493 |
|
| Activity Added |
Feb 27, 2009 |
1547 |
|
| Activity Added |
Feb 05, 2009 |
1569 |
|
| Field Status Added |
Jan 27, 2009 |
1578 |
|
| Field Updated |
Dec 01, 2008 |
1635 |
|
| Project Description Added |
Nov 24, 2008 |
1642 |
|
| Activity Added |
Oct 22, 2008 |
1675 |
|
| Activity Added |
Sep 30, 2008 |
1697 |
|
| Activity Added |
Sep 16, 2008 |
1711 |
|
| Activity Added |
Sep 05, 2008 |
1722 |
|
| Field Status Added |
Jun 02, 2008 |
1817 |
|
| Field Status Added |
Apr 24, 2008 |
1856 |
|
| Activity Added |
Apr 24, 2008 |
1856 |
|
| Field Added |
Apr 24, 2008 |
1856 |
|
| Field Status Added |
Apr 21, 2008 |
1859 |
|
| Field Status Added |
Apr 03, 2008 |
1877 |
|
| Field Status Added |
Feb 04, 2008 |
1936 |
|
| Field Added |
Feb 04, 2008 |
1936 |
|
| Field Added |
Dec 30, 2007 |
1972 |
|
| Field Status Added |
Dec 30, 2007 |
1972 |
|
| Facility Status Added |
Dec 28, 2007 |
1974 |
|
| Field Status Added |
Dec 28, 2007 |
1974 |
|
| Facility Added |
Dec 28, 2007 |
1974 |
|
| Field Added |
Dec 28, 2007 |
1974 |
|
| Activity Added |
Oct 30, 2007 |
2033 |
|
| Activity Added |
Aug 09, 2007 |
2115 |
|
| Activity Added |
May 10, 2007 |
2206 |
|
| Activity Added |
Feb 12, 2007 |
2293 |
|
| Activity Added |
Jan 24, 2007 |
2312 |
|
| Activity Added |
Apr 04, 2006 |
2607 |
|
| Activity Added |
Mar 10, 2006 |
2632 |
|
| Activity Added |
Dec 22, 2005 |
2710 |
|
| Activity Added |
Oct 19, 2005 |
2774 |
|
| Activity Added |
Aug 08, 2005 |
2846 |
|
| Activity Added |
Jun 29, 2005 |
2886 |
|
| Activity Added |
Feb 09, 2005 |
3026 |
|
| Activity Added |
Dec 09, 2004 |
3088 |
|
| Activity Added |
Nov 23, 2004 |
3104 |
|
| Activity Added |
Sep 02, 2003 |
3552 |
|
Project Update History Search - View all the lastest updates made by the SubseaIQ team.
|
|
| Facility Name |
Gomez Hub (ATP Innovator) |
|
| Duty |
Oil/Gas |
|
| Operator |
ATP |
|
| Current Status |
Producing since 2006 |
|
| Host Type |
FPU/FPS |
|
| Water Depth |
914 m / 3,016 ft |
|
| Dev.Cost |
$80,000,000 |
| |
| Region |
US |
| |
| Location |
Mississippi Canyon 711 |
| Field Name |
Gomez |
|
| Discovery Date |
Dec 1997 |
|
| Block |
Mississippi Canyon 711 |
|
| Reserve Type |
Oil/Gas |
|
| Current Status |
Producing |
|
| Production Start |
Mar 2006 |
|
| Water Depth |
914 m / 3,016 ft |
| Field Name |
Anduin |
|
| Discovery Date |
Feb 2005 |
|
| Block |
Mississippi Canyon 755 |
|
| Reserve Type |
Oil |
|
| Current Status |
Producing |
|
| Production Start |
Oct 2007 |
|
| Water Depth |
732 m / 2,416 ft |
| Field Name |
Gladden |
|
| Discovery Date |
Apr 2008 |
|
| Block |
Mississippi Canyon 800 |
|
| Reserve Type |
Oil |
|
| Current Status |
Producing |
|
| Production Start |
Feb 2011 |
|
| Water Depth |
950 m / 3,135 ft |
| Field Name |
Anduin West |
|
| Discovery Date |
Apr 2008 |
|
| Block |
Mississippi Canyon 754 |
|
| Reserve Type |
Oil/Gas |
|
| Current Status |
Producing |
|
| Production Start |
Feb 2011 |
|
| Water Depth |
822 m / 2,713 ft |
|